Meaning
A progress claim (مستخلص) is the statement a contractor submits, usually monthly, of the work executed on a contract up to a date. It lists each item of the bill of quantities with the quantity done so far and its contract rate, so the total is cumulative: the value of all work to date. The client's engineer or consultant measures the work and certifies the claim, sometimes for less than was claimed.
What is due for the period is the certified total to date less what earlier claims already certified, then less what the contract deducts: the retention held until handover, and the recovery of any advance payment. An interim claim is one of the series during the work; the final claim settles the contract's whole value after handover, with variations and deductions agreed.
In the books the certified amount is revenue for the contractor and is invoiced as a tax invoice; the retention is a receivable that is not yet due. Work done but not yet certified is not invoiced, and is followed on the project as work in progress.
Also called: mustakhlas · payment certificate · interim payment certificate · progress billing · مستخلص
Example
Al Noor Contracting's fourth claim on a warehouse shows work to date of 800,000.00, and the consultant certifies it in full. Earlier claims certified 600,000.00, so the period is 200,000.00. Al Noor invoices 200,000.00 plus 15% VAT of 30,000.00, 230,000.00 in all; the contract holds back 10%, 23,000.00, so 207,000.00 is due now and 23,000.00 at handover.